Mar 2015
|
The NSW Government announced $200 million for the project.
|
Mar 2016
|
Arup was awarded the contract to develop the Environmental Impact Statement (EIS) and finalise the concept design.
|
May 2018
|
The Federal Government announced $971 million for the project.
|
Sep 2018
|
The NSW Government released the preferred concept design for the Coffs Harbour bypass for public comment. The preferred concept design incorporates land bridges at Gatelys Road and Roberts Hill, and cuttings at Gatelys Road and Shephards Lane. The concept design states the Benefit Cost Ratio (BCR) for the project is 1.3 with the projected cost of the project being between $1.17 billion to $1.3 billion.
|
Jan 2019
|
The NSW Government announced, following community feedback, that changes would be made to the preferred design, including the use of tunnels that can be accessed by all vehicles. The preferred concept design stated that long tunnels were no longer being considered to ensure all vehicles carrying dangerous good could use the bypass. The Coffs Harbour bypass Community Consultative Committee has been established to drive engagement on the project.
|
Jun 2020
|
The NSW Government released the Submissions and Amendments Reports for the Coffs Harbour Bypass following exhibition of the project’s Environmental Impact Statement.
|
Jul 2020
|
Transport for NSW issued a Request for Tenders for geotechnical investigations and consulting for the project. Tender applications closed on 27 August 2020. The RFT comes after the National Cabinet announced on 24 July that the Coffs Harbour Bypass is among 15 projects that will be fast tracked in response to the COVID-19 pandemic.
|
Sep 2020
|
Transport for NSW announced the commencement of a Market Interaction Process that will involve registration, provision of documentation to eligible participants, an online briefing, technical and interactive sessions, and a submission process, with registrations to be part of the process closing on 25 September.
|
Sep 2020
|
The Environmental Impact Statement was released. Submissions on the EIS closed on 27 October 2019. The EIS process has seen the estimated cost of the project rise from $1.2 billion to $1.8 billion due to revisions to the concept design.
|
Nov 2020
|
The NSW Government granted environmental approval for the project under the Environmental Planning and Assessment Act 1979 (NSW), subject to conditions.
|
Dec 2020
|
The Federal Government has approved the project under the Environment Protection and Biodiversity Conservation Act.
|
Dec 2020
|
Early works commenced.
|
Apr 2021
|
Transport for NSW opened a Request for Tender (RFT) process for the provision of transaction management services, closing 6 May.
|
Jun 2021
|
Transport for NSW called for pre-registrations of interest for delivery of the Coffs Harbour Bypass, closing on 16 July.
|
Jun 2021
|
The 2021-22 NSW Budget provided continued funding towards the Coffs Harbour Bypass by allocating $1.2 billion over the next four years, including $100 million in FY2021-22.
|
Oct 2021
|
Transport for NSW shortlisted three bidders for the project. The shortlisted bidders are a CPB and WeBuild Joint Venture, ACCIONA and Seymour Whyte Joint Venture and Gamuda and Ferrovial Joint Venture.
|
May 2022
|
Transport for NSW issued a Request for Tender (RFT) for the Provision of a Tunnel Technical Lead, closing 2 June.
|
Jun 2022
|
The New South Wales Government awarded the Design and Construct contract for the Coffs Harbour Bypass to a Ferrovial and Gamuda Joint Venture. The project 's total estimated cost has increased to $2.2 billion.
|
Jun 2022
|
The 2022-23 NSW Budget committed $1.4 billion over four years to the project, including $246 million in FY2022-23.
|
Aug 2022
|
Transport for NSW awarded Aurecon the contract to act as Independent Certifier on the Coffs Harbour Bypass project.
|
Sep 2022
|
Arcadis was appointed the lead designer on the project.
|
Mar 2023
|
Major works commenced on the project. The bypass is expected to be open to traffic from late 2026 and fully completed in late 2027.
|
Sep 2023
|
The NSW Government released its Detailed Design Consultation summary report for the project.
|