The NSW Government has announced the redevelopment of Penrith Stadium. The scope of the works includes:
- demolition of the western stand
- play facilities catering for both male and female sporting teams
- new amenities and food and beverage offerings
- refurbishment of the eastern stand
- new stadium entries, and
- warm-up space on the western field.
The redevelopment is expected to increase the venue’s capacity to 25,000 from 22,500.
Key Dates
| Sep 2023 | Project Announcement |
| May 2024 | EOIs Open |
| Mar 2025 | Contract Award |
| Apr 2025 | Construction Commencement |
| Dec 2026 | Expected Construction Completion |
Funding contributions
| NSW Government |
Procurement
| Procuring Agency: | Infrastructure NSW |
| Shortlist: | AW Edwards Hansen Yuncken John Holland |
| Successful Tenderer: | John Holland |
| Related contracts: |
PROJECT HISTORY
| Nov 2022 | A scoping report and request for the Secretary's Environmental Assessment Requirements were published for the project. |
| Sep 2023 | The NSW Government announced that $309 million in funding would be allocated to the redevelopment of Penrith Stadium over the forward estimates period, with $48 million allocated for FY2023-24. The 2023-24 NSW Budget Papers stated that the final project scope will be considered by the Government in FY2023-24. |
| Jan 2024 | The NSW Government released the proposed design concept for the project. The design concept includes a new western grandstand and a redeveloped eastern grandstand, which would increase the ground capacity to 25,000, as well as new food and beverage outlets and new player facilities, including four new change rooms. |
| Mar 2024 | The NSW Government submitted an updated Scoping Report to the Department of Planning, Housing, and Infrastructure, requesting the Secretary’s Environmental Assessment Requirements for the project's preparation of an Environmental Impact Statement. |
| Apr 2024 | The NSW Government issued the Secretary’s Environmental Assessment Requirements for the Penrith Stadium Refurbishment. |
| May 2024 | The NSW Government opened Expressions of Interest for the Main Works contract to deliver the Penrith Stadium Redevelopment, closing on 31 May. |
| Jul 2024 | Shortlisted tenderers for the main works contract were announced. |
| Nov 2024 | The NSW Government has announced that the Department of Planning, Housing and Infrastructure has granted the project planning consent. |
| Mar 2025 | John Holland was awarded the main works contract to deliver the stadium and the surrounding entertainment precinct. |
| Apr 2025 | Construction commenced on the project. |
| Jun 2025 | The Budget has allocated $279 million over four years to the redevelopment, including $208 million in FY2025-26. |
Estimated Total Cost
(2023)
Sector
Social
Procurement approach
Traditional Procurement |
Location
New South Wales |
Resources