Sydney Water has proposed a new pre-treatment plant at Propsect Resovoir, to increase processing capacity of the existing Prospect Treatment Plant. The facility will have an initial capacity of 500 megalitres per day.
The project includes development of a new facility upstream of the existing site to assist the water network following periods where water quality has been impacted. Future works include upgrades to the existing treatment plant and installation of a new tilling gate.
Key Dates
| May 2023 | EOIs Open | 
| Jun 2023 | EOIs Close | 
| Dec 2024 | Contract Award | 
| Apr 2025 | Construction Commencement | 
| 2026 | Expected Construction Completion | 
Procurement
| Procuring Agency: | Sydney Water | 
| Successful Tenderer: | ACCIONA and SUEZ Water Joint Venture | 
| Procurement note: | The project has been procured through a Design and Construct Contract.  | 
                     
PROJECT HISTORY
| May 2023 | Sydney Water called for Expressions of Interest for the project. | 
| Dec 2024 | Sydney Water awarded the contract for the project to an ACCIONA and SUEZ Water Joint Venture. The contract, valued at $322 million does not include future stages of the program. The total program cost is estimated to be $838 million. | 
| Apr 2025 | ACCIONA announced that construction has commenced on the project. | 
| May 2025 | The NSW Independent Pricing and Regulatory Tribunal's (IPART) released its Draft Determination on Sydney Water’s pricing proposal. IPART's draft decision is to defer most of Sydney Water’s Pretreatment Program, includes Prospect Pre-Treatment Plant Upgrades. IPART's final Determination in due in September, with submissions on the Draft Determination closing 23 June. | 
| Jun 2025 | The 2025-2026 NSW Budget allocated $757 million to the project – however the Independent Pricing and Regulatory Tribunal’s (IPART) draft determination for the 2025-2030 regulatory period excludes this project and it is unclear from the Budget papers how the funding for this project is profiled over the forward estimates period. | 
                     Estimated Total Cost
                  
                  
                                          
                        (2024)
                     
                  
               Sector
               Water & Sewerage
            Procurement approach
               
                                                               Traditional Procurement  | 
                                                      
            Location
               
                                                               New South Wales |
                                                      
               Resources