The Queen Elizabeth II Jubilee Hospital Expansion is expected to deliver 112 new beds to the existing hopsital, as well as a new purpose-built elective surgery facility.
The project is part of the Queensland Government's Hospital Rescue Plan.
Key Dates
| Jun 2022 | Project Announcement |
| Oct 2022 | EOIs Open |
| Nov 2022 | EOIs Close |
| May 2023 | Contract Award |
| 2024 | Construction Commencement |
| 2028 | Expected Construction Completion |
Funding contributions
| Queensland Government |
Procurement
| Procuring Agency: | Queensland Health |
| Successful Tenderer: | Built |
| Procurement note: | The project is being procured as a part of the Queensland Government's Capacity Expansion Program (CEP). The CEP will deliver $9.8 billion worth of new and upgraded hospitals across 15 separate projects. CEP projects are being procured using a Pre-Qualified Panel model. Under the model, interested parties submit EOIs outlinining the list of projects or ‘bundles of projects’ they wish to participate in. Contractors successfully appointed to the panel will then be selected to participate in a Request for Tenders (RFT) phase for particular projects, or packages of projects. |
| Related contracts: |
PROJECT HISTORY
| Jun 2022 | The project was confirmed as having been funded through the Capacity Expansion Program. |
| Oct 2022 | Expressions of Interest (EOIs) to join a prequalified panel to deliver Capacity Expansion Program projects was released. |
| May 2023 | The Queensland Government awarded the contract to deliver the project to Built under a Managing Contractor model. |
| Jun 2023 | GHD was appointed as the lead architect for the project. |
| Sep 2024 | The project cost has increased from $465 million to $620 million following the design phase due to scope modifications, cost escalations and to account for complexity. The Government has stated the cost increases will be covered through the existing $11.2 billion Program allocation. This includes an additional $1 billion in "equity funding" allocated to the Program in the 2024-25 Queensland Budget. |
| Apr 2025 | The Queensland Government released its Hospital Rescue Plan and response to the 42 recommendations made by the Independent Review of Queensland Health’s Capacity Expansion Program. The Plan states that the six projects awarded Stage Two contracts as part of the two-stage Managing Contractor model by the former Government in late-2024, including the QEII Hospital Expansion, will continue as currently contracted. |
| Jun 2025 | The 2025-26 Queensland Budget confirmed a total estimated cost of $621 million for the project, with $200 million allocated in FY2025-26. |
| Dec 2025 | The Queensland Government confirmed a revised construction completion date of 2028 for the project. |