Project

Queensland Supergrid South

PROJECT STATUS
Prospective
Queensland Supergrid South

The Queensland SuperGrid South is a proposed upgrade and extension, linking Central and South Queensland energy grids. The project is Stage Two of the Queensland Energy and Jobs plan, and involves new 500-kilovolt (kV) transmission lines to connect Borumba Pumped Hydro Project into the NEM in Central Queensland.

The project involves 430 kilometres of 500-kV transmission lines: 

  • The Borumba connection: two 500-kV transmission lines around 140 kilometres in length, and
  • The Southern Queensland and Central Queensland connection: one 500-kV transmission line around 290 kilometres in length. 

This is an actionable project under AEMO's 2024 ISP.

Key Dates

Dec 2031 Expected Construction Completion

PROJECT HISTORY

Sep 2022 The Queensland Government identified the need for the project in its Queensland SuperGrid Infrastructure Blueprint. The Blueprint estimated that the Borumba connection construction would be required to commence in FY2026 and be complete by FY2029 for operation commencement in 2030. The estimated cost was $800 million. The Blueprint estimated that CQ and SQ construction would be required to commence in FY2027 and be complete by FY2030 for operation commencement in 2031. The estimated cost was $1.3 billion.
Dec 2023 The project was identified as an Actionable ISP Project in the draft 2024 AEMO Integrated Systems Plan. The project cost was also updated to an estimated $3.3 billion ± 50 per cent and an updated construction completion date of June 2031 was identified.
Jun 2024 AEMO's final 2024 Integrated Systems Plan confirmed the project's total estimated cost as $3.3 billion ± 50 per cent and updated the completion date to December 2031.
Estimated Total Cost
(2023)
Sector
Energy
Procurement approach
Traditional Procurement |
Location
Queensland |
Resources
Major Contract

Borumba Pumped Hydro Transmission Connections

PROJECT STATUS
Announced
Borumba Pumped Hydro Transmission Connections

The Borumba Pumped Hydro Transmission Connections project will link the future Borumba Pumped Hydro Project to two points in the Queensland grid: Woolooga in the north, and Halys in the south west. 

The Borumba to Halys transmission connection will be a 106-kilometre, 500 kV connection. It has the ability to co-locate with existing Powerlink transmission lines around Tarong Power Station and Halys Substation for 26 kilometres of its length.

The Borumba to Woologa transmission connection will be a 90-kilometre, 500 kV connection. The corridor captures an existing Energy Queensland distribution line in the northern portion of the corridor for 15 kilometres of its length. 

The project is expected to be complete by the time the Borumba Dam Pumped Hydro project is operational.

Key Dates

2026 Expected Construction Commencement
2029 Expected Construction Completion

PROJECT HISTORY

Dec 2021 Initial stakeholder consultation commences.
Sep 2022 The Queensland Government releases their Queensland Supergrid Infrastructure Blueprint. It identifies the Borumba Pumped Hydro Transmission Connections project as two transmission connections of 80 and 60 kilometres each (140 kilometres total) and notes the preliminary cost estimate as $800 million.
Nov 2022 Powerlink released corridor options for connections to the Woolooga and Halys substations. This includes five options for Borumba to Halys
Apr 2023 Powerlink released their draft decision on the two transmission corridors, indicating the 88 km Woolooga West Corridor and the 105 km Halys Central (Option A) were the preferred options.
Sep 2023 Powerlink confirmed its final corridor selection for the Borumba to Halys section, confirming Halys Central (Option A) as the selected corridor and identifying the new corridor length as 106 km.
Nov 2023 Powerlink confirms the final corridor selection for the Borumba to Woolooga section, confirming Woolooga West as the selected corridor and identifying the new corridor length as 90 km.
Apr 2024 Powerlink updated estimated construction dates, indicating construction is expected to commence in 2026 and be complete in 2029.
Sector
Energy
Procurement approach
Other |
Location
Queensland |
Resources
Project pages
Powerlink project page