Rangebank BESS

PROJECT STATUS
Operational
Rangebank BESS

The proposed Rangebank Battery Energy Storage System (BESS) is a 200-megawatt/400-megawatt-hour battery to be located in the Rangebank Business Park in southeast Melbourne. It will connect to the Cranbourne Terminal Station.

Key Dates

Apr 2023 Contract Award
Jun 2023 Construction Commencement
Dec 2024 Construction Completion

Financing

Macquarie Asset Management’s Green Investment Group and Shell Energy Operations are partnering to deliver the battery. 

Through an offtake agreement, Shell Energy will have access to 100 per cent of the battery’s offtake over a 20-year period.

Procurement

Procuring Agency: Shell Energy
Successful Tenderer: Fluence
Procurement note:

The project is being delivered under a "Build, Service, and Maintain" contract over the lifespan of the project.

PROJECT HISTORY

Mar 2023 Macquarie Asset Management’s Green Investment Group and Shell Energy Operations announced they would deliver the project.
Apr 2023 Fluence were selected to deliver the main works contract for the project. Fluence is responsible for the construction, service and maintenance of the BESS facility over the project lifespan.
Dec 2024 The Victorian Government announced the completion of construction on the project.