The Redcliffe Hospital expansion will add capacity for 204 beds to the existing facility, as well as a range of other new and upgraded facilities.
The expansion a refurbishment of the existing hospital to deliver additional capacity and the integration of the clinical services and ambulatory care buildings,
The expansion will include:
- additional operating theatres
- Emergency Department treatment spaces
- endoscopy rooms
- birthing suites
- outpatient consult rooms
- diagnostic rooms, and
- expansion of medical imaging, pharmacy and pathology areas.
Key Dates
| Jun 2022 | Project Announcement |
| Nov 2025 | ROIs Open |
| Aug 2026 | Preferred Bidder Selection |
| 2032 | Expected Construction Completion |
Funding contributions
| Queensland Government |
Procurement
| Procuring Agency: | Queensland Health |
| Successful Tenderer: | Lendlease |
| Procurement note: | The project was initially procured as a part of the Queensland Government's Capacity Expansion Project (CEP). CEP projects are being procured using a Pre-Qualified Panel model. Under the model, interested parties submit EOIs outlinining the list of projects or ‘bundles of projects’ they wish to participate in. Contractors successfully appointed to the panel will then be selected to participate in a Request for Tenders phase for particular projects, or packages of projects. Following the release of the Hospital Rescue Plan, the Queensland Government committed to redesign and rescoping of the project, with procurement to be run following this process. |
| Related contracts: |
PROJECT HISTORY
| Jun 2022 | The project was confirmed as having been funded through the Capacity Expansion Program. |
| Oct 2022 | Expressions of Interest (EOIs) to join a prequalified panel to deliver Capacity Expansion Program projects was released. |
| Jun 2023 | Multiplex was appointed as Managing Contractor to deliver the $1.1 billion hospital expansion. The Queensland Government also announced the project's total estimated cost had increased by $88 million to $1.148 billion, due to an expanded scope. The $88 million will be allocated from the Capacity Expansion Program's Contingency Fund and will to integrate the ambulatory care and clinical services buildings into one facility. |
| Feb 2024 | The Queensland Government announced early works had commenced on the project. |
| Apr 2025 | The Queensland Government released its Hospital Rescue Plan and response to the 42 recommendations made by the Independent Review of Queensland Health’s Capacity Expansion Program. The Review recommended pausing early site works and engaging with the Stage One contractor - Multiplex - to review the project. In response, the Government accepted the recommendation and committed to further design review and potential rescoping as outlined in the Rescue Plan. The Review also confirmed the project's total estimated cost, as originally scoped, has increased from $1.1 billion to $2.1 billion, however, this is subject to change through the re-planning process. The expected completion date was also delayed from the Q4 2028 to Q4 2030. |
| Nov 2025 | The Queensland Government commenced Registrations of Interest for the main works contract for the project. Registrations close 21 November. |
| Dec 2025 | The Queensland Government announced an updated masterplan was finalised for the project as part of the Hospital Resuce Plan. Construction is expected to be completed in 2032, with beds to be delivered from late 2027. |
| Aug 2026 | Lendlease were selected as the preferred bidder to deliver the Redcliffe Hospital Expansion. The project will be delivered under an Early Contractor Involvement model. Full project completion is expected in 2032, with beds to be progressively delivered from late 2027. |