PROJECT STATUS
Under Delivery
Reeves Plains Battery Stage One

The Reeves Plains Battery forms part of the Reeves Plains Energy Hub, to be located in Reeves Plains, South Australia, which will comprise two batteries and a 300-megawatt (MW) gas-fired power station.

The battery component will be delivered over two stages:

  • Stage 1: 250 MW battery with four hours of storage.
  • Stage 2: Additional 250 MW battery with a further 4 hours of storage capacity, totalling 500 MW of capacity.

Further details on the delivery of Stage 2 of the battery are yet to be announced.

Key Dates

Jun 2025 Contract Award
Jan 2026 Construction Commencement
Dec 2028 Expected Construction Completion

Procurement

Procuring Agency: Alinta Energy
Successful Tenderer: GenusPlus Group
Related contracts:
Battery modules
Successful Tenderer - Contemporary Amperex Technology

Inverters
Successful Tenderer - Power Electronics

PROJECT HISTORY

Sep 2024 Alinta Energy confirmed the contract had recieved development approval exemption from the South Australian Government, following endorsment as an 'essential infrastructure' project.
Dec 2024 Geotechnical works commenced at the site
Jun 2025 Alinta Energy awarded GenusPlus Group as the Principal Contractor to deliver Stage One.
Aug 2025 Alinta Energy reached financial close on Stage One of the project.
Sep 2025 The project was awarded a Capacity Investment Scheme Agreement as part of the Capacity Investment Scheme Tender Round Three.
Jan 2026 Main works construction started on the project.