Richmond Road - Elara Boulevard to Heritage Road

PROJECT STATUS
Under Delivery
Richmond Road - Elara Boulevard to Heritage Road

Richmond Road is an arterial road linking Richmond and Blacktown in Sydney's north-west. The Elara Boulevard to Heritage Road section of the project involves:

  • widening 900 metres of Richmond Road from two lanes to four lanes 
  • new traffic lights 800 metres north west of Elara Boulevard
  • new bus priority lanes at the main intersection, and 
  • widening the central median for future widening of the road to six lanes, if needed.

 

Key Dates

May 2025 RFT Open
Jul 2025 RFT Close
Dec 2025 Contract Award
Jan 2026 Construction Commencement
2028 Expected Construction Completion

Funding contributions

Federal Government
NSW Government

The Federal Government has allocated $75 million for the section north of Elara Boulevard.

The NSW Government has allocated $157 million for the section north of Elara Boulevard, $100 million of which is from the Urban Roads Fund. 

Procurement

Procuring Agency: Transport for NSW
Successful Tenderer: Daracon

PROJECT HISTORY

Mar 2022 The 2022-23 Federal Budget allocated $25 million for the section from Elara Boulevard to Heritage Road, Marsden Park.
Feb 2023 The NSW Government committed $100 million for the Elara Boulevard section of the Richmond Road Upgrade.
Nov 2023 As part of the project changes resulting from the Independent Strategic Review of the Federal Infrastructure Investment Program, the Federal Government committed an additional $50 million the Elara Boulevard to Heritage Road section.
Jun 2024 The NSW Government allocated an additional $100 million to the project via the Urban Roads Fund in the 2024-25 State Budget, bringing the total allocation over 4 years to $156.5 million. A total cost was not confirmed.
Feb 2025 Infrastructure NSW released an updated procurement and delivery timeline for the project in its 2025 Major Projects Pipeline. Procurement is expected to commence in Q2 2025, with a contract scheduled to be awarded in Q3 2025. Construction is expected to commence in Q1 2026 and be complete in Q2 2027.
May 2025 TfNSW issued a Request for Tender for the main works contract, closing 2 July.
Dec 2025 Daracon were awarded the contract to deliver the project.
Jan 2026 Main works construction commenced on the project.