Richmond Road Upgrade

PROJECT STATUS
Under Delivery
Richmond Road Upgrade

Richmond Road is an arterial road linking Richmond and Blacktown in Sydney's north-west. The road has been progressively upgraded to service growth in the area.

Upgrades are being undertaken across two main sections of Richmond Road:

  • M7 Motorway to Townson Road: widening the 2.2-kilometre section to six lanes and building a new off-ramp bridge to connect Richmond Road to Westlink M7, and
  • north of Elara Boulevard, Marsden Park: widening a section of approximately 900 metre section towards Heritage Road to four lanes, widening the central median to allow for six lanes in future, and new traffic lights 800 metres north of Elara Boulevard.

Key Dates

Mar 2022 Project Announcement
Jan 2026 Construction Commencement
Dec 2028 Expected Construction Completion

Funding contributions

Federal Government
NSW Government

The Federal Government has allocated $260 million for the M7 to Townson Road section and $75 million for the section north of Elara Boulevard.

The NSW Government has allocated $317 million for the M7 to Townson Road section, and $157 million for the section north of Elara Boulevard. Respectively, $285 million and $100 million of these allocations are from the Urban Roads Fund. 

The project was partly funded by the NSW Government through the WestInvest program.

Procurement

Procuring Agency: Transport for NSW

PROJECT HISTORY

Feb 2023 The NSW Government committed $385 million towards the upgrade, comprising $285 million for the M7 to Townson Road section and $100 million for the section north of Elara Boulevard.
Nov 2023 As part of the project changes resulting from the Independent Strategic Review of the Federal Infrastructure Investment Program, the Federal Government committed an additional $50 million the Elara Boulevard to Heritage Road section.
Jan 2026 Main works construction commenced on the project.
Estimated Total Cost
(2024)
Sector
Road
Procurement approach
Unconfirmed |
Location
New South Wales |
Resources
Tender notices
ROI Tender page
Project contact information
Major Contract

Richmond Road - M7 Motorway to Townson Road

PROJECT STATUS
Under Delivery
Richmond Road - M7 Motorway to Townson Road

Richmond Road is an arterial road linking Richmond and Blacktown in Sydney's north-west. The M7 Motorway to Townson Road section of the project involves:

  • widening 2.2 kilometres of Richmond Road between the M7 Motorway and Townson Road, adding an additional lane in each direction
  • a new flyover bridge from the M7 Motorway Rooty Hill Road North off-ramp to Richmond Road 
  • replacing the bridge over Bells Creek, with new separated pedestrian and bike paths and travel lanes
  • new staged pedestrian crossings on Richmond Road at Alderton Drive and Townson Road, and 
  • upgrades to intersections. 

Key Dates

Oct 2025 Contract Award
Jan 2026 Construction Commencement
Dec 2028 Expected Construction Completion

Funding contributions

Federal Government
NSW Government

The Federal Government has allocated $260 million for the M7 to Townson Road section. The NSW Government has allocated $317 million for the M7 to Townson Road section, $285 million of which is from the Urban Roads Fund. 

Procurement

Procuring Agency: Transport for NSW
Successful Tenderer: Gamuda Australia and DT Infrastructure
Related contracts:
Design and Construct
Successful Tenderer - Gamuda Australia and DT Infrastructure

PROJECT HISTORY

Feb 2023 The NSW Government committed $285 million for the M7 to Townson Road section.
May 2024 The 2024-25 Federal Budget allocated an additional $260 million to the M7 Motorway to Townson Road section.
Jun 2024 The NSW Government allocated $316.5 million over 4 years to the project in the 2024-25 State Budget, though a total cost was not confirmed.
Sep 2024 Transport for NSW (TfNSW) has commenced a Registration of Interest (ROI) process for a main works contractor to deliver the Richmond Road Upgrade between M7 Motorway and Townson Road.
Feb 2025 Infrastructure NSW released updated procurement and delivery timelines for the project. A contract expected to be awarded by the end of the year, with construction scheduled to commence in the first quarter of 2026. The project is expected to be completed by the end of 2028.
Jul 2025 Infrastructure NSW released an updated timeline for the project in its 2025 Major Projects Pipeline. Construction is scheduled to commence in Q1 2026. The project is expected to be completed by Q1 2029.
Oct 2025 Transport for NSW awarded the design and construction contract to a joint venture of Gamuda Australia and DT Infrastructure.
Jan 2026 Construction commenced on the project, with Transport for NSW also announcing the project is expected to be completed by December 2028.
Estimated Total Cost
(2025)
Sector
Road
Procurement approach
Design and Construct (D&C) |
Location
New South Wales |
Resources
Government resources
Infrastructure NSW Pipeline 2030
Tender notices
2024/09/30 - ROI
Major Contract

Richmond Road - Elara Boulevard to Heritage Road

PROJECT STATUS
Under Delivery
Richmond Road - Elara Boulevard to Heritage Road

Richmond Road is an arterial road linking Richmond and Blacktown in Sydney's north-west. The Elara Boulevard to Heritage Road section of the project involves:

  • widening 900 metres of Richmond Road from two lanes to four lanes 
  • new traffic lights 800 metres north west of Elara Boulevard
  • new bus priority lanes at the main intersection, and 
  • widening the central median for future widening of the road to six lanes, if needed.

 

Key Dates

May 2025 RFT Open
Jul 2025 RFT Close
Dec 2025 Contract Award
Jan 2026 Construction Commencement
2028 Expected Construction Completion

Funding contributions

Federal Government
NSW Government

The Federal Government has allocated $75 million for the section north of Elara Boulevard.

The NSW Government has allocated $157 million for the section north of Elara Boulevard, $100 million of which is from the Urban Roads Fund. 

Procurement

Procuring Agency: Transport for NSW
Successful Tenderer: Daracon

PROJECT HISTORY

Mar 2022 The 2022-23 Federal Budget allocated $25 million for the section from Elara Boulevard to Heritage Road, Marsden Park.
Feb 2023 The NSW Government committed $100 million for the Elara Boulevard section of the Richmond Road Upgrade.
Nov 2023 As part of the project changes resulting from the Independent Strategic Review of the Federal Infrastructure Investment Program, the Federal Government committed an additional $50 million the Elara Boulevard to Heritage Road section.
Jun 2024 The NSW Government allocated an additional $100 million to the project via the Urban Roads Fund in the 2024-25 State Budget, bringing the total allocation over 4 years to $156.5 million. A total cost was not confirmed.
Feb 2025 Infrastructure NSW released an updated procurement and delivery timeline for the project in its 2025 Major Projects Pipeline. Procurement is expected to commence in Q2 2025, with a contract scheduled to be awarded in Q3 2025. Construction is expected to commence in Q1 2026 and be complete in Q2 2027.
May 2025 TfNSW issued a Request for Tender for the main works contract, closing 2 July.
Dec 2025 Daracon were awarded the contract to deliver the project.
Jan 2026 Main works construction commenced on the project.
Estimated Total Cost
(2024)
Sector
Road
Procurement approach
Traditional Procurement |
Location
New South Wales |
Resources