The Richmond Valley Solar Farm is a proposed Hybrid Solar Farm, being developed by Ark Energy, to be located approximately seven kilometres east of Rappville in the Northern Rivers region of NSW.
The scope of the Richmond Valley Solar Farm includes:
- solar farm with a capacity of 435 megawatts (MW)
- battery with capacity of 475 MW / 2,200 megawatt hours (MWh)
- construction of a substation, and
- installation of a two-kilometre 330 kilovolt (kV) transmission line and associated infrastructure.
Key Dates
| 2027 | Expected Construction Commencement |
| 2029 | Expected Construction Completion |
Financing
| Equity Finance: | Korea Zinc |
| Debt Finance: | Korea Zinc |
Procurement
| Procuring Agency: | Ark Energy |
| Successful Tenderer: | Elecnor |
| Procurement note: | Elecnor has signed an Early Contractor Involvement Agreement with project developers Ark Energy to undertake early works prior to the formal execution of an EPC contract. |
| Related contracts: |
PROJECT HISTORY
| Jul 2022 | The proponent submitted the scoping report to the NSW State Government and requested SEARs. |
| Sep 2022 | The NSW Department of Planning and Environment issued the Planning Secretary's Environmental Assessment Requirements (SEARs) for the project. |
| Dec 2023 | The 275 megawatt / 2,200 megawatt hour, 8-hour storage battery component of the project was selected in AEMO Services' third tender round under the NSW Electricity Infrastructure Roadmap to enter into a Long-Term Energy Service Agreement. |
| Jul 2024 | The Environmental Impact Statement submitted by Ark Energy was placed on exhibition, with consultation closing on 21 August 2024. |
| Mar 2025 | The project was included in the Federal Government's inaugural Renewable Energy Priority List. The Priority List aims to provide coordinated support through Federal, state and territory regulatory and environmental approval processes on a case-by-case basis and provide a 'faster to yes, faster to no' approach to regulatory approvals. |
| Mar 2025 | Hanwha Energy was selected for the manufacture, delivery and installation of the BESS component of the project. |
| Sep 2025 | Elecnor entered into an Early Contractor Involvement with Ark Energy to deliver early works for the project, prior to the formal award of an EPC Contract. |
| Oct 2025 | The NSW Government granted planning and development approval to the project. |
| Dec 2025 | The Federal Government granted EPBC approval under the Environment Protection and Biodiversity Conservation Act 1999 for the project. |
| Jun 2026 | AEMO granted grid connection approval to the project. Additionally, project developers Ark Energy announced an updated construction start date of late-2026. |
| Jul 2026 | Ark Energy has reached a final investment decision for the first stage of the project. The financing package comprises $586 million in equity and $716 million in debt finance. The first stage of the project includes the delivery of a 200-MW solar farm and a 275-MW / 2,200-MWh BESS. |
Estimated Total Cost
(2024)
Sector
Energy
Procurement approach
Engineering, Procurement and Construction (EPC) |
Location
New South Wales |
Resources
Media releases
2025/10/16 - NSW Development Approval2025/03/12 - BESS supply contract signed
2025/09/29 - ECI/EPC Contract Awarded
2026/06/05 - Connection Approval
2026/07/24 - Financial Investment Decision