Project

Sandy Creek BESS

PROJECT STATUS
Prospective
Sandy Creek BESS

The Sandy Creek (Muswelbrook) BESS project involves the construction of a grid-connected Battery Energy Storage System with an installed capacity of approximately 750 megawatts / 1,500 mehawatt hours. The facility will be located on a 35-hectare site at Sandy Creek Road, McCully’s Gap, nar Muswellbrook in Central West NSW.

 

Key Dates

2028 Expected Construction Commencement
2029 Expected Construction Completion

Procurement

Procuring Agency: Edify Energy Pty Ltd

PROJECT HISTORY

Apr 2025 A Scoping Report was lodged with the NSW Department of Planning, Housing and Infrastructure (DPHI), initiating the SSD application process.
Jun 2025 The NSW Department of Planning, Housing and Infrastructure issued Secretary’s Environmental Assessment Requirements (SEARs) for the project
Sector
Energy
Procurement approach
Other |
Location
New South Wales |
Resources