Sandy Creek Solar Farm

PROJECT STATUS
Detailed Planning
Sandy Creek Solar Farm

The proposed Sandy Creek Solar Farm would comprise a 700-megawatt (MW) solar farm and 700-MW / 2,800-megawatt hour Battery Energy Storage System.

The project is to be located 25 kilometres southwest of Dunedoo, in the NSW Central West Orana REZ.

Key Dates

Apr 2022 Project Announcement
Jun 2027 Expected Construction Commencement

Financing

The project's proponent, Lightsource BP, will develop and finance the project.

Procurement

Procuring Agency: lightsource bp

PROJECT HISTORY

Apr 2022 Lightsource BP submitted a Scoping Report and requested the Secretary's Environmental and Assessment Requirements (SEARs).
Mar 2024 The NSW Government has issued the SEARs following assessment under Australia's national environment law.
Mar 2024 The Federal Government announced the project has received environmental planning approval and a revision of the planned capacity of the solar farm from 750 megawatts to 840 megawatts.
May 2024 The project's Environmental Impact Statement (EIS) was published and the project placed on exhibition, closing 25 June. The EIS indicated a revised proposal of a 700 megawatt (MW) solar farm and 2,800 MWh battery, reduced from 840 MW and 3,000 MWh respectively.
Dec 2024 The project was selected for the Federal Capacity Investment Scheme Tender Round One.
May 2025 EnergyCo granted access rights to 10 projects to connect to the NSW Central-West Orana Renewable Energy Zone, including the Sandy Creek Solar Farm and Battery.
Aug 2026 LightSource BP published updated construction timelines in the August 2026 Community Update for the project. Construction is now expected to commence in the second quarter of 2027.
Estimated Total Cost
(2024)
Sector
Energy
Procurement approach
Unconfirmed |
Location
New South Wales |
Resources
Project pages
Lightsource BP