The South Pacific Offshore Wind Project is a proposed 1.6-gigawatt offshore wind farm located in the Illawarra Offshore Wind Area.The scope includes 105 floating wind turbine generators.
The project has been proposed by BlueFloat energy.
Key Dates
| Jan 2028 | Expected Construction Commencement |
| Dec 2030 | Expected Construction Completion |
PROJECT HISTORY
| Jun 2024 | The Federal Government formally declared the Illawarra offshore wind zone. The South Pacific Wind Farm project falls into this declared offshore wind zone. |
| Feb 2025 | The Federal Government announced that consideration of a feasibility license application by BlueFloat Energy for the project has been paused at the proponent’s request until after the 2025 Federal election. |
| Jan 2026 | The Federal Government announced that it would not be awarding feasibility licences to any project located in the Illawarra offshore Wind Zone |