Project

Papakura ki Pukekura - Papakura to Bombay

PROJECT STATUS
Announced
Papakura ki Pukekura - Papakura to Bombay

The Papakura ki Pukekura - Papakura to Bombay project involves upgrades to the State Highway 1 (SH1) between Papakura and Bombay. The project is planned to be delivered in two stages. 

Stage One of the project involves upgrades to State Highway 1 (SH1) between Papakura and Drury South. This is being delivered in stages. The first stage includes widening the SH1 to three lanes in each direction from Papakura interchange to Otūwairoa (Slippery Creek), replacement of the Park Estate Road Bridge and a new noise wall.

Stage Two is proposed to upgrade the road from Drury Interchange (Stage 1B1) to Bombay. The proposal includes new interchanges at Drury South, Ramamara, and Bombay. Though both stages were originally funded through the New Zealand Upgrade Program, a re-evaluation completed in June 2021 resulted in the deferral of Stage Two. There is currently no funding allocated for Stage Two. 

 

Key Dates

Apr 2021 Construction Commencement: Stage 1
2027 Expected Construction Completion

Funding contributions

NZ Government

Procurement

Procuring Agency: Waka Kotahi NZ Transport Agency

PROJECT HISTORY

Apr 2018 The four-kilometre upgrade was included as a new project in the transport investment priorities of the Auckland Transport Alignment Project, for the 2018-2028 decade.
Jun 2019 The design and consenting phase began to refine the preferred option and route, and prepare consent applications.
Jan 2020 New Zealand Government announced $423 million in funding for the project, as part of the NZ Upgrade Program
Mar 2021 The 2021-31 investment package of the Auckland Transport Alignment Project included Papakura to Drury South project as a fully funded commitment.
Apr 2021 Construction commenced on Stage 1, with the 1A section getting underway.
Jun 2021 Following a re-evaluation of the New Zealand Upgrade Program, Stage Two of the project was deferred from the program's scope. Whether Stage Two would proceed through a different funding stream was not confirmed.
Estimated Total Cost
(2021)
Sector
Road
Procurement approach
Traditional Procurement |
Location
New Zealand |
Resources
Major Contract

Papakura ki Pukekura - Papakura to Drury Stage One

PROJECT STATUS
Under Delivery
Papakura ki Pukekura - Papakura to Drury Stage One

Stage One of the Papakura ki Pukekura - Papakura to Bombay will widen the motorway to three lanes in each direction between Papakura and Drury. 

The scope of the works includes:

  • 4.5 km of new traffic lanes 
  • widened shoulders to enable future bus services
  • 4 km of new paths for people walking and cycling
  • interchange improvements at Papakura, including a new southbound on-ramp
  • interchange improvements at Drury, enabling rail electrification, and
  • improved safety barriers, lighting and noise mitigation. 

The project has been divided into three stages: 

  • Stage 1A - Upgrades to SH1 between Papakura and Otūwairoa/Slippery Creek 
  • Stage 1B1 - Active transport path between Papakura and Drury alongside the northbound lane of SH1, rebuilding the Papkura Interchange to enable the electrification of the Papakura to Pukekohe rail line, and 
  • Stage 1B2 - New Otūwairoa/Slippery Creek bridge.

Key Dates

Jul 2020 ROIs Open
Oct 2020 RFT Open
Mar 2021 Contract Award
Apr 2021 Construction Commencement - Stage 1A
Jul 2022 Expected Construction Commencement - Stage 1B1
2027 Expected Construction Completion

Funding contributions

NZ Government

Procurement

Procuring Agency: Waka Kotahi NZ Transport Agency
Successful Tenderer: Fulton Hogan

PROJECT HISTORY

May 2020 Waka Kotahi NZ Transport Agency issued Advanced Notice of Information announcing the start of procurement, closing on 3 June 2020.
Jul 2020 Waka Kotahi NZ Transport Agency opened the Registrations of Interest process for the project.
Oct 2020 Waka Kotahi NZ Transport Agency released the Request for Tender to shortlisted candidates.
Mar 2021 Contract for the first package of works One was awarded to Fulton Hogan.
Apr 2021 Construction on Stage 1A commenced.
Jul 2021 Applications for environmental consent were lodged for Stage 1B1 of the project.
Nov 2021 Consent approval was granted for Stage 1B1 of the project for a new walking and cycling path, and an upgraded Drury interchange to enable rail electrification. Stage 1B1 physical works were expected to begin in early 2022, with the construction of new raised bridges at Drury interchange, and construction of the main interchange anticipated to begin in mid-2023.
Jun 2023 Stage 1B2 of the SH1 Papakura to Drury project received consent approval under the COVID-19 Recovery (Fast-track Consenting) Act.
Estimated Total Cost
(2024)
Sector
Road
Procurement approach
Traditional Procurement |
Location
New Zealand |
Resources