The Stoney Creek Wind Farm is a proposed 166-megawatt wind farm located 80 kilometres south-west of Bundaberg, Queensland.
The scope of the project includes construction of up to 27 turbines and supporting infrastructure, including a battery of unspecified capacity.
The project proponent is Greenleaf Renewables.
Key Dates
| Dec 2027 | Expected Construction Commencement |
| Jun 2029 | Expected Construction Completion |
Procurement
| Procuring Agency: | Greenleaf Renewables |
PROJECT HISTORY
| Mar 2023 | The project received development approval from the Queensland Government. |
| Oct 2023 | Greenleaf Renewables submitted preliminary documentation at the request of DCCEEW for further evaluation. |
| Dec 2023 | The Federal Government approved the development of the project. |
| Oct 2025 | Greenleaf Renewables announced its acquisition of the project. |
| Nov 2025 | The proposed transmission line route for the project was submitted to the EPBC Portal for assessment. |
| Dec 2025 | The Federal Department of Climate Change, Energy, the Environment and Water determined that the proposed transmission development was not a controlled action and would not require assessment under the EPBC Act. |
| Apr 2026 | Greenleaf Renewables announced updated delivery timelines for the project. Construction is expected to commence in late 2027 and commence operations by mid-2029. |
Estimated Total Cost
(2025)
Sector
Energy
Procurement approach
Engineering, Procurement and Construction (EPC) |
Location
Queensland |
Resources