Project

Suburban Rail Loop

PROJECT STATUS
Detailed Planning
Suburban Rail Loop

The Suburban Rail Loop (SRL) is a 90-kilometre rail loop of the Melbourne metropolitan area. SRL will connect to every major rail line from the Frankston Line to the Werribee Line. As a result, the SRL will transition Melbourne's rail network from its current radial status to an oribital network. 

The Loop will consist of three sections:

  • SRL East - Cheltenham to Box Hill
  • SRL North - Box Hill to Melbourne Airport
  • SRL West - Melbourne Airport to Werribee

The precincts to be connected by SRL include: Cheltenham, Clayton, Monash, Glen Waverley, Burwood, Box Hill, Doncaster, Heidelberg, Bundoora, Reservoir, Fawkner, Broadmeadows, Melbourne Airport, Sunshine and Werribee.

As well as providing a rail link to the airport, the project will also build three 'transport super hubs' at Clayton, Broadmeadows and Sunshine to connect regional passengers to the Suburban Rail Loop.

Given the scale of the Loop, construction is to be staged over several decades, with the SRL East and SRL North sections to be constructed first. The west section will be planned and constructed in conjunction with the Melbourne Metro Tunnel, Melbourne Airport Rail and the Western Rail Plan.

The SRL East and SRL North sections have a preliminary costing in the range of $30 to $50.5 billion. A timeline and estimated cost for the completion of SRL West has not been provided at this stage.

The first stage of the Suburban Rail Loop – SRL East – is a fully-tunnelled 26 kilometre metro corridor between Cheltenham in the South and Box Hill in the North. The line will include six stations, including new interchanges with existing heavy rail stations at Cheltenham, Clayton, Glen Waverley and Box Hill, with new stations at Monash and Burwood. The new interchange in Clayton will act as a 'transport super hub, connecting regional passengers to the Suburban Rail Loop.

The six underground stations will range from 17 to 23 metres below street level and will be built using a 'bottom-up' method. The location of the entrances will be near existing train stations and central amenities.

SRL East has been split into seven work packages: 

  • Works Package A: Initial and Early Works
    • site establishment
    • utility relocation and protection works
    • road and traffic modifications
    • tunnel Access Shaft structures
    • drainage and civil works
    • ground Improvement works, and
    • temporary works and tram works
  • Works Package B: Power Construction Supply Works
    • connecting Suburban Rail Loop East to Victoria’s shared electricity network, and
    • construction of onsite substations
  • Works Package C: Cheltenham to Glen Waverley Tunnels
    • tunnelling and cross passages between Cheltenham and Glen Waverley, and
    • Clayton and Monash station box excavations, including temporary retaining structures
  • Works Package D: Glen Waverley to Box Hill Tunnels 
    • tunnelling and cross passages between Glen Waverley and Box Hill
    • Burwood and Glen Waverley station box excavations, including temporary retaining structures, and
    • an intervention shaft structure
  • Works Package E: Cheltenham to Glen Waverley Stations
    • station building works at Cheltenham, Clayton and Monash
    • station box excavation at Cheltenham, including temporary retaining structures
    • all station work to complete stations, excluding work included in Works Package G, and
    • surface work at station precincts
  • Works Package F: Glen Waverley to Box Hill Stations
    • station building works at Glen Waverley, Burwood and Box Hill
    • station box excavation at Box Hill, including temporary restraining structures
    • all station work to complete stations, excluding work included in Works Package G, and
    • surface work at station precincts
  • Works Package G: Linewide
    • tunnel fit-out works
    • cross passage fit-out
    • permanent high and low voltage power supply
    • traction power
    • track sectioning equipment
    • communication systems
    • network control, including signalling
    • rolling stock
    • depot and maintenance facilities
    • backup network control and disaster recovery centre
    • overall responsibility for systems integration, and
    • operations and maintenance.

Key Dates

Aug 2018 Project Announcement
2022 Expected Contract Award (SRL East)
2022 Expected Construction Commencement (SRL East)
2035 Expected Construction Completion (SRL East)
2035 Expected Construction Commencement (SRL North)

Funding contributions

Federal Government
Victorian Government

Procurement

Procuring Agency: Suburban Rail Loop Authority
Related contracts:
Commercial Adviser
Successful Tenderer - KPMG

Planning and Design related Technical services
Successful Tenderer - A Joint Venture of Aurecon, Jacobs and Mott MacDonald

PROJECT HISTORY

Aug 2018 Prior to the State election, then Victorian Government announced that it will start work on Suburban Rail Loop if re-elected.
Jun 2019 Registrations of Interest were called for enabling the Government to assess market capacity to deliver the project. This ROI process is not a pre-qualification for any formal procurement process.
Sep 2019 The Victorian Government established the Suburban Rail Loop Authority (SRLA) to manage and lead development on the project.
Nov 2019 The Victorian Government announced the SRL will be serviced by a new fleet of trains that will be four to five carriages long and be capable of travelling at higher speeds than the existing fleet. The shorter train design will also result in shorter station platforms.
Jul 2021 SRLA released an Advance Notice of a Request for Tender (RFT) for Technical Advisory Services. RFTs were expected to open in August.
Aug 2021 SLRA opened a Request for Tender (RFT) for Technical Advisory Services to support the development and delivery of the Suburban Rail Loop project, closing on 6 October. SLRA noted that the scope of Technical Advisory Services may expand subject to further approvals during the term of its engagement.
Aug 2021 The Victorian Government released the project's Business and Investment Case. The document outlines estimated costs and timelines for SRL East and North. The document detailed changes to the staging of the project, which will be delivered as SRL East, SRL North and SRL West.
Sep 2021 The Victorian Government introduced the Suburban Rail Loop Bill 2021 (Vic) to Parliament. The Bill seeks to formally establish the Suburban Rail Loop Authority (SRLA) and confers on the SRLA the authority to plan, deliver, and operate the Suburban Rail Loop and manage associated developments.
Oct 2021 The Parliament of Victoria passed the Suburban Rail Loop Bill 2021. The Bill formally establishes the Suburban Rail Loop Authority (SRLA) and confers the authority for the SRLA to plan, deliver, and operate the Suburban Rail Loop and manage associated developments.
Feb 2022 The Suburban Rail Loop Authority (SRLA) issued a Request for Tender (RFT) for the establishment of a Planning and Delivery Services Panel to support SRLA's Rail and Infrastructure Delivery Division. The services covered in the RFT are split into four Panel Group Categories, including Technical Services; Project Delivery Services; Land Planning, Environment Sustainability Services; and Precinct Planning and Development Services. The RFT closed on 25 March 2022.
Mar 2022 The SRLA opened a joint Expressions of Interest (EOIs) phase for the Suburban Rail Loop (SRL) East tunnelling packages - Works Package C – Tunnels – Cheltenham to Glen Waverley, and Works Package D – Tunnels – Glen Waverley to Box Hill.
May 2022 The Suburban Rail Loop Authority issued a Request for Tender (RFT) for an Independent Environmental Auditor on the Suburban Rail Loop East project. RFTs close on 20 June 2022.
Jun 2022 The SRLA announced construction had commenced on SRL East - Works Package A - Early Works.
Aug 2022 SRL East received planning approval.
Oct 2022 The 2022-23 October Federal Budget allocated $2.2 billion towards the Suburban Rail Loop East project.
Mar 2024 The Victorian Parliamentary Budget Office published updated cost forecasts for the SRL East and SRL North. SRL East is expected to cost $32.8 billion to construct, with an estimated $51.4 billion operating cost over the first 50 years of service.
Major Contract

SRL East - Works Package G - Linewide

PROJECT STATUS
Under Procurement
SRL East - Works Package G - Linewide

The first stage of the Suburban Rail Loop – SRL East – is a fully-tunnelled 26-kilometre metro corridor between Cheltenham in the South and Box Hill in the North. The line will include six stations, including new interchanges with existing heavy rail stations at Cheltenham, Clayton, Glen Waverley and Box Hill, with new stations at Monash and Burwood.

The Suburban Rail Loop Authority has separated SRL East into seven packages. Included in the scope of Works Package G is:

  • tunnel fit-out works
  • cross passage fit-out
  • permanent high and low voltage power supply
  • traction power
  • track sectioning equipment
  • communication systems
  • network control, including signalling
  • rolling stock
  • depot and maintenance facilities
  • backup network control and disaster recovery centre
  • overall responsibility for systems integration, and
  • operations and maintenance.

Key Dates

Dec 2021 Project Announcement
Jul 2023 EOIs Open
2025 Expected Contract Award
Dec 2025 Expected Construction Commencement
Dec 2025 Expected Construction Completion

Procurement

Procuring Agency: Suburban Rail Loop Authority
Shortlist: TransitLinX, comprising John Holland, RATP Dev, Alstom, KBR and WSP; and UrbanLeap, comprising Gamuda Engineering, Keolis Downer, Siemens, AECOM, GHD, Hyundai Rotem and Downer Rail.

PROJECT HISTORY

Oct 2021 The SRLA released indicative details of all seven packages for the delivery of SRL East.
Nov 2021 The SRLA released the SRL East Environmental Effects Statement.
Dec 2023 The SRLA announced two consortia had been shortlisted to deliver the project. Shortlisted bidders include TransitLinX, comprising John Holland, RATP Dev, Alstom, KBR and WSP; and UrbanLeap, comprising Gamuda Engineering, Keolis Downer, Siemens, AECOM, GHD, Hyundai Rotem and Downer Rail. The contract is expected to be awarded in 2025.
Sector
Rail
Procurement approach
Alliance | Service Contract |
Location
Victoria |
Resources
Project website
SRL East
Media releases
2023/12/12
Major Contract

SRL East - Works Package A - Development, Initial, and Early Works

PROJECT STATUS
Under Delivery
SRL East - Works Package A - Development, Initial, and Early Works

The Suburban Rail Loop East - Development, Initial, and Early Works package includes:

  • road modifications
  • utility relocations
  • ground improvement trials 
  • tram terminus works, and 
  • site preparations for tunnel boring machines.

 

Key Dates

Nov 2020 Project Announcement
Nov 2021 Contract Award
2022 Construction Commencement

Funding contributions

Victorian Government

Procurement

Procuring Agency: Suburban Rail Loop Authority
Shortlist: - CPB Contractors, John Holland, and Laing O'Rourke
Successful Tenderer: Laing O'Rourke

PROJECT HISTORY

Nov 2020 The Victorian Government allocated $2.2 billion for early works in its 2020/21 Budget.
Dec 2020 The Victorian Government opened Expressions of Interest for the early works contract.
May 2021 CPB Contractors, John Holland, and Laing O'Rourke shortlisted for the early works project.
Nov 2021 The Victorian Government awarded the contract to Laing O'Rourke.
Jun 2022 The SRLA announced Construction had commenced on SRL East - Works Package A - Early Works.
May 2023 In the 2023-24 Victorian Budget, the previously named Suburban Rail Loop – Initial and Early Works package was renamed as Suburban Rail Loop East – Development, Initial and Early Works, and received $574 million for FY2023-24. The estimated cost of the package also increased by $12 million to $2.4 billion, with construction completion estimated by mid-2025.
Estimated Total Cost
(2023)
Sector
Rail
Procurement approach
Traditional Procurement |
Location
Victoria |
Resources
Tender notices
2020/12/15
Major Contract

SRL East - Works Package D - Tunnels - Glen Waverley to Box Hill

PROJECT STATUS
Awarded
SRL East - Works Package D - Tunnels - Glen Waverley to Box Hill

The first stage of the Suburban Rail Loop – SRL East – is a fully-tunnelled 26-kilometre metro corridor between Cheltenham in the South and Box Hill in the North. The line will include six stations, including new interchanges with existing heavy rail stations at Cheltenham, Clayton, Glen Waverley and Box Hill, with new stations at Monash and Burwood.

The Suburban Rail Loop Authority has separated SRL East into seven packages. Included in the scope of Works Package D is:

  • 10 kilometres of twin tunnelling and cross passages between Glen Waverley and Box Hill
  • Burwood and Glen Waverley station box excavations, including temporary retaining structures, and 
  • an intervention shaft structure.

Key Dates

Mar 2022 EOIs Open
Jul 2024 Preferred Bidder Selection
Nov 2024 Contract Award

Procurement

Procuring Agency: Suburban Rail Loop Authority
Tenderers (EOI/ROI): Bouygues Construction Australia, a CPB Contractors, Ghella and ACCIONA Joint Venture, a John Holland and Gamuda Joint Venture, a Samsung C&T Corporation and Hyundai Engineering & Construction Joint Venture, and a Webuild and GS Engineering and Construction Joint Venture.
Shortlist: John Holland and Gamuda, and Webuild and GS E&C.
Successful Tenderer: Terra Verde - A consortium of WeBuild, GS Engineering and Construction, Bouygues Construction Australia
Procurement note:

The SRLA is procuring the SRL East tunnelling packages - Works Package C – Tunnels – Cheltenham to Glen Waverley, and Works Package D – Tunnels – Glen Waverley to Box Hill via a joint Expressions of Interest (EOIs) phase. The joint EOI phase will see three bidders shortlisted and advanced to a staggered Request for Proposal (RFP) phase, where bidders will first compete for Package C, with a contract expected to be awarded by the end of 2023. The two remaining unsuccessful bidders for Package C will then compete for Package D, with that contract expected to be awarded in the third quarter of 2024.

Works are being delivered using an Incentivised Target Cost model. 

PROJECT HISTORY

Dec 2021 The SRLA opened a Pre-Qualification phase for Works Package C and D, closing 25 March. Pre-qualified participants will progress to the Expressions of Interest phase.
Mar 2022 The SRLA opened a joint Expressions of Interest (EOIs) phase for the Suburban Rail Loop (SRL) East tunnelling packages - Works Package C – Tunnels – Cheltenham to Glen Waverley, and Works Package D – Tunnels – Glen Waverley to Box Hill.
Jun 2022 The SRLA announced five bidders had progressed through the EOI phase for SRL East tunnelling packages - Works Package C and Works Package D.
Sep 2022 The Victorian Government announced the shortlist for the delivery of SRL East tunnelling packages – Works Package C and Works Package D.
Dec 2023 Following the awarding of Works Package C, the two remaining shortlisted bidders – a consortium comprising John Holland and Gamuda, and a consortium comprising Webuild, GS E&C Australia, and Bouygues Construction Australia – will now enter a Request for Proposals (RFP) phase for Works Package D.
Jul 2024 The Victorian Government announced the preferred bidder for Works Package D as Terra Verde - a consortium of WeBuild, GS Engineering and Construction, Bouygues Construction Australia.
Nov 2024 The Victorian Government formally awarded the contract for Works Package D to Terra Verde. Additionally, the Victorian Government published an estimated cost of $1.7 billion for the project.
Estimated Total Cost
(2024)
Sector
Rail
Procurement approach
Other |
Location
Victoria |
Resources
Major Contract

SRL East - Works Package F - Stations - Glen Waverley to Box Hill

PROJECT STATUS
Under Procurement
SRL East - Works Package F - Stations - Glen Waverley to Box Hill

The first stage of the Suburban Rail Loop – SRL East – is a fully-tunnelled 26-kilometre metro corridor between Cheltenham in the South and Box Hill in the North. The line will include six stations, including new interchanges with existing heavy rail stations at Cheltenham, Clayton, Glen Waverley and Box Hill, with new stations at Monash and Burwood.

The Suburban Rail Loop Authority has separated SRL East into seven packages. Included in the scope of Works Package F is:

  • station building works at Glen Waverley, Burwood and Box Hill
  • station box excavation at Box Hill, including temporary restraining structures
  • all station work to complete stations, excluding work included in Works Package G, and
  • surface work at station precincts

Key Dates

Dec 2021 Project Announcement
Nov 2024 Shortlist Announced
Jun 2026 Expected Contract Award

Procurement

Procuring Agency: Suburban Rail Loop Authority
Shortlist: Place Alliance (comprising John Holland, Arup and Kellogg Brown and Root), Eastern Stations Precinct Alliance (Lendlease and WSP) and Connexus Alliance (CPB, Multiplex and GHD).
Procurement note:

The Suburban Rail Loop - Stations Packages are being procured using a 3-2-1 model. Three shortlisted bidders have been announced for Package F which will be awarded first. Following the award of Package F, the remaining two shortlisted bidders will compete for Package E. 

PROJECT HISTORY

Nov 2021 The Suburban Rail Loop Authority (SRLA) released the SRL East Environmental Effects Statement.
Dec 2021 The SRLA released indicative details of all seven packages for the delivery of SRL East.
Nov 2024 The shortlist for the delivery of Works Package E and F was announced. Shortlisted bidders include; Place Alliance (comprising John Holland, Arup and Kellogg Brown and Root), Eastern Stations Precinct Alliance (Lendlease and WSP) and Connexus Alliance (CPB Contractors, Multiplex and GHD).
Sector
Rail
Procurement approach
Alliance |
Location
Victoria |
Resources
Project website
SRL East
Major Contract

SRL East - Works Package E - Stations - Cheltenham to Glen Waverley

PROJECT STATUS
Under Procurement
SRL East - Works Package E - Stations - Cheltenham to Glen Waverley

The first stage of the Suburban Rail Loop – SRL East – is a fully-tunnelled 26-kilometre metro corridor between Cheltenham in the South and Box Hill in the North. The line will include six stations, including new interchanges with existing heavy rail stations at Cheltenham, Clayton, Glen Waverley and Box Hill, with new stations at Monash and Burwood.

The Suburban Rail Loop Authority has separated SRL East into seven packages. Included in the scope of Works Package E is:

  • station building works at Cheltenham, Clayton and Monash
  • station box excavation at Cheltenham, including temporary retaining structures
  • all station work to complete stations, excluding work included in Works Package G, and
  • surface work at station precincts

Key Dates

Dec 2021 Project Announcement
Nov 2024 Shortlist Announced

Procurement

Procuring Agency: Suburban Rail Loop Authority
Shortlist: Place Alliance (John Holland, Arup and Kellogg Brown and Root), Eastern Stations Precinct Alliance (Lendlease and WSP) and Connexus Alliance (CPB, Multiplex and GHD)
Procurement note:

The Suburban Rail Loop East - Stations Packages are being procured using a 3-2-1 model. Three shortlisted bidders have been announced for Package F which will be awarded first. Following the award of Package F, the remaining two shortlisted bidders will compete for Package E. Package F is expected to be awarded in 2026.

PROJECT HISTORY

Nov 2021 The Suburban Rail Loop Authority (SRLA) released the SRL East Environmental Effects Statement.
Dec 2021 The SRLA released indicative details of all seven packages for the delivery of SRL East.
Feb 2024 Victorian Government announced early works had commenced.
Nov 2024 The shortlist for the delivery of Works Package E and F was announced. Shortlisted bidders include; Place Alliance (comprising John Holland, Arup and Kellogg Brown and Root), Eastern Stations Precinct Alliance (Lendlease and WSP) and Connexus Alliance (CPB Contractors, Multiplex and GHD).
Sector
Rail
Procurement approach
Traditional Procurement | Alliance | Unconfirmed |
Location
Victoria |
Resources
Project website
SRL East
Major Contract

SRL East - Works Package C - Tunnels - Cheltenham to Glen Waverley

PROJECT STATUS
Awarded
SRL East - Works Package C - Tunnels - Cheltenham to Glen Waverley

The first stage of the Suburban Rail Loop – SRL East – is a fully-tunnelled 26-kilometre metro corridor between Cheltenham in the South and Box Hill in the North. The line will include six stations, including new interchanges with existing heavy rail stations at Cheltenham, Clayton, Glen Waverley and Box Hill, with new stations at Monash and Burwood.

The Suburban Rail Loop Authority (SRLA) has separated SRL East into seven packages. Included in the scope of Works Package C is:

  • tunnelling and cross passages over the 16-kilometre Cheltenham and Glen Waverley section, and
  • Clayton and Monash station box excavations, including temporary retaining structures.

Key Dates

Mar 2022 EOIs Open
Aug 2023 Preferred Bidder Selected
Dec 2023 Contract Award
2026 Expected Construction Commencement

Procurement

Procuring Agency: Suburban Rail Loop Authority
Tenderers (EOI/ROI): Bouygues Construction Australia; a CPB Contractors, Ghella and ACCIONA Joint Venture; a John Holland and Gamuda Joint Venture; a Samsung C&T Corporation and Hyundai Engineering & Construction Joint Venture; and a Webuild and GS Engineering and Construction Joint Venture.
Shortlist: CPB Contractors, Ghella, and ACCIONA; John Holland and Gamuda; and Webuild and GS E&C.
Successful Tenderer: CPB Contractors, Ghella, and ACCIONA.
Procurement note:

The SRLA is procuring the SRL East tunnelling packages - Works Package C – Tunnels – Cheltenham to Glen Waverley, and Works Package D – Tunnels – Glen Waverley to Box Hill via a joint Expressions of Interest (EOIs) phase. The joint EOI phase will see three bidders shortlisted and advanced to a staggered Request for Proposal (RFP) phase, where bidders will first compete for Package C, with a contract expected to be awarded by the end of 2023. The two remaining unsuccessful bidders for Package C will then compete for Package D, with that contract expected to be awarded in the third quarter of 2024. Works will be delivered using an Incentivised Target Cost contract.

Related contracts:
Tunnel Boring Machine supplier
Successful Tenderer - Herrenknecht

PROJECT HISTORY

Dec 2021 The SRLA opened Pre-Qualification for Works Package C and D, closing on 25 March 2022. Pre-qualified participants were to progress to the Expressions of Interest phase.
Mar 2022 The SRLA opened a joint Expressions of Interest (EOIs) phase for the Suburban Rail Loop (SRL) East tunnelling packages - Works Package C – Tunnels – Cheltenham to Glen Waverley, and Works Package D – Tunnels – Glen Waverley to Box Hill.
Jun 2022 The SRLA announced five bidders had progressed through the EOI phase for SRL East tunnelling packages - Works Package C and Works Package D.
Sep 2022 The Victorian Government announced the shortlist for the delivery of SRL East tunnelling packages – Works Package C and Works Package D.
Aug 2023 The Victorian Government announced the Suburban Connect consortium, comprising CPB Contractors, Ghella and ACCIONA Construction had been selected as the preferred bidder to deliver Works Package C.
Dec 2023 The Victorian Government formally awarded the Suburban Connect consortium, comprising CPB Contractors, Ghella and ACCIONA Construction, the contract for the delivery of works package C.
Apr 2024 The Victorian Government announced that Suburban Connect, the consortium delivering Package C, is calling for Expressions of Interest from suppliers. Tunnelling is expected to commence in 2026.
Sep 2024 The Victorian Government announced Herrenknecht as the preferred provider to supply four tunnel boring machines for the Suburban Rail Loop East - Works Package C. Tunnelling is expected to commence in 2026.