Sundown Solar Farm

PROJECT STATUS
Announced
Sundown Solar Farm

The Sundown Solar Farm is a proposed 360 megawatt (MW) photovoltaic array to be located approximately 30km east of Inverell, NSW. The scope of the works includes:

  • a 360-MW solar farm comprising 660,000 solar panels
  • a 150-MW / 600-MWh battery storage system
  • a 330-kilovolt on-site substation, and 
  • other ancillary works for the delivery and maintenance of the project. 

PROJECT HISTORY

Nov 2017 A scoping report was released for the project alongside a request for the Secretary's Environmental Assessment Requirements (SEARs).
Aug 2020 SEARs were issued for the project.
Aug 2022 The project was referred to the EPBC Portal for Federal environmental approvals.
Aug 2022 Supplementary SEARs were issued for the project.
Aug 2022 The Federal Department of Climate Change, Energy, the Environment and Water declared that the project constituted a 'controlled action ' and would be assessed under an assessment bilateral agreement with New South Wales.
Jul 2023 The Environmental Impact Statement (EIS) was placed on public exhibition, closing 3 August.
Aug 2026 The NSW Independent Planning Commission granted development approval to the project.
Estimated Total Cost
(2023)
Sector
Energy
Procurement approach
Traditional Procurement | Other |
Location
New South Wales |