The Sydney Metro City & Southwest - Tunnel and Station Excavation Works includes 15.5km of twin tunnels between Chatswood and Marrickville. The full project scope includes:
-
15.5km twin running tunnels each of approximately six metres internal diameter
-
cross passages between the running tunnels
-
demolition, excavation and concrete structure for dives at Chatswood and Marrickville
-
demolition and excavation works for new stations at Crows Nest, Victoria Cross, Barangaroo, Martin Place, Pitt Street and Waterloo, and
-
four mined caverns for a rail crossover at Barangaroo and new stations at Victoria Cross, Martin Place and Pitt Street
Key Dates
| Aug 2017 | Contract Award |
| Oct 2018 | Construction Commencement |
| Mar 2020 | Construction Completion |
Funding contributions
| NSW Government |
Procurement
| Procuring Agency: | Transport for NSW |
| Successful Tenderer: | A John Holland, CPB Contractors and Ghella Joint Venture |
| Procurement note: | The project was procured through a fixed price Design and Construct contract. |
| Related contracts: |
PROJECT HISTORY
| Jun 2016 | Transport for NSW published the EIS for the City and Southwest project. The EIS outlines preliminary plans for new city metro stations and enabling facilities along the proposed metro line. |
| Aug 2017 | The contract for the project was awarded to a John Holland, CPB Contractors, and Ghella Joint Venture. Seperatley, Independent Certifier Services for the project were awarded to APP Corporation. |
| Oct 2018 | Works commenced on the project, with Tunnel Boring Machine Nancy launched from Marrickville. |
| Mar 2020 | Work concluded on the project following the end of tunnelling. |
Estimated Total Cost
(2017)
Sector
Rail
Procurement approach
Traditional Procurement |
Location
New South Wales |