Sydney Metro - City and South West - Tunnel and Station Excavation

PROJECT STATUS
Operational
Sydney Metro - City and South West - Tunnel and Station Excavation

The Sydney Metro City & Southwest - Tunnel and Station Excavation Works includes 15.5km of twin tunnels between Chatswood and Marrickville. The full project scope includes: 

  • 15.5km twin running tunnels each of approximately six metres internal diameter

  • cross passages between the running tunnels

  • demolition, excavation and concrete structure for dives at Chatswood and Marrickville

  • demolition and excavation works for new stations at Crows Nest, Victoria Cross, Barangaroo, Martin Place, Pitt Street and Waterloo, and

  • four mined caverns for a rail crossover at Barangaroo and new stations at Victoria Cross, Martin Place and Pitt Street

Key Dates

Aug 2017 Contract Award
Oct 2018 Construction Commencement
Mar 2020 Construction Completion

Funding contributions

NSW Government

Procurement

Procuring Agency: Transport for NSW
Successful Tenderer: A John Holland, CPB Contractors and Ghella Joint Venture
Procurement note:

The project was procured through a fixed price Design and Construct contract.

Related contracts:
Independent Certifier Services
Successful Tenderer - APP Corporation

PROJECT HISTORY

Jun 2016 Transport for NSW published the EIS for the City and Southwest project. The EIS outlines preliminary plans for new city metro stations and enabling facilities along the proposed metro line.
Aug 2017 The contract for the project was awarded to a John Holland, CPB Contractors, and Ghella Joint Venture. Seperatley, Independent Certifier Services for the project were awarded to APP Corporation.
Oct 2018 Works commenced on the project, with Tunnel Boring Machine Nancy launched from Marrickville.
Mar 2020 Work concluded on the project following the end of tunnelling.
Estimated Total Cost
(2017)
Sector
Rail
Procurement approach
Traditional Procurement |
Location
New South Wales |
Resources
Government resources
EIS