The Parramatta Enabling Works Package for Sydney Metro West will be delivered ahead of the Tunnel and Excavation – Western Package. The Parramatta Enabling Works package includes the following scope of works:
Demolition work consisting of:
- a multi-level car park, 13 buildings and redundant substations
- protection of properties adjacent to the site, and
- protection and retention of two heritage listed properties within the site.
Utilities work consisting of:
- decommissioning and removal of five substations and installation of one new switching station
- cut and cap of a gas pipe
- decommissioning of all utility connections to buildings to be demolished
- relocation of a fibre optic cable, and
- heritage and archaeology investigations related to utility relocations.
Internal roadworks consisting of:
- construction of two public access roads, and
- heritage and archaeology investigations related to roadworks.
Key Dates
Feb 2021 | EOIs Open |
Sep 2022 | Expected Contract Award |
Jun 2023 | Expected Construction Commencement |
Dec 2024 | Expected Construction Completion |
Procurement
Procuring Agency: | Sydney Metro |
PROJECT HISTORY
Oct 2020 | The Package was announced as part of the Transport for NSW's Transport Infrastructure Pipeline 2025. The potential delivery type for the package was noted as a Design and Construct contract. |
Feb 2021 | The NSW Government, through Sydney Metro, opened Expressions of Interest for Pre-Qualification for the Sydney Metro West – Parramatta Enabling Works package. An industry briefing was held on 5 February. |
Estimated Total Cost
(2021)
Sector
Rail
Procurement approach
Traditional Procurement |
Unconfirmed |
Location
New South Wales |
Resources