Takanini Level Crossings Removal

PROJECT STATUS
Awarded
Takanini Level Crossings Removal

The Takanini Level Crossings Removal project involves the construction of seven bridges across the Southern Line, between Te Mahia Station and Walters Road. 

The full scope of the project includes delivery of:

  • Three new vehicle bridges at Manuia Road, Taka Street, and Walters Road,
  • Four new pedestrian bridges, and
  • Roading upgrades.

Key Dates

Dec 2025 Contract Award
Dec 2027 Expected Construction Commencement
2032 Expected Construction Completion

Procurement

Procuring Agency: Auckland Transport
Successful Tenderer: Fulton Hogan
Procurement note:

The project is being delivered through a Construct-Only Early Contractor Involvement (ECI) contract.

Related contracts:
Design Services
Successful Tenderer - Aecom-Jacobs JV

PROJECT HISTORY

Jul 2024 The project was included in the Auckland Regional Land Transport Plan 2024-2034.
Aug 2025 Auckland Transport awarded programme design and consenting services to an Aecom-Jacobs joint venture.
Dec 2025 Auckland Transport awarded Fulton Hogan the main works Early Contractor Engagment contract to deliver the project.
Estimated Total Cost
(2025)
Sector
Rail
Procurement approach
Traditional Procurement |
Location
New Zealand |