Project

Taranaki Base Hospital Redevelopment Stage Two

PROJECT STATUS
Operational
Taranaki Base Hospital Redevelopment Stage Two

Stage Two of the hospital redevelopment included construction of a new East Wing. The new building includes:

  • emergency department
  • Intensive Care Unit
  • rooftop helipad
  • maternity facilities and delivery suite
  • new postnatal ward and neonatal unit
  • upgraded laboratory and radiology services, and
  • morgue.

Beyond the East Wing, the project also includes the construction of

  • Cancer Centre
  • Acute Services Building, and
  • Renal Unit

Stage One of the project, also referred to as Project Maunga was completed in 2014.

Key Dates

Sep 2019 Project Announcement
Jul 2020 Contract Award
May 2021 Construction Commencement - East Wing Building
2023 Construction Commencement - Cancer Centre
Dec 2025 Expected Construction Completion
Jun 2026 Construction Completion - East Wing Building

Funding contributions

NZ Government

Procurement

Procuring Agency: Taranaki District Health Board
Successful Tenderer: Leighs Construction - ECI Contract (including Main Works)
Related contracts:
Architect (East Wing Building)
Successful Tenderer - Warren and Mahoney

Building Services Engineering (East Wing Building)
Successful Tenderer - Beca

Cost Consultant (East Wing Building)
Successful Tenderer - Rider Levett Bucknall

Structural Engineering (East Wing Building)
Successful Tenderer - Holmes

PROJECT HISTORY

2018 Four of the existing hospitals were found to be seismically compromised. As part of the Seismic Risk Management Plan, the project was developed to deliver a new Renal Unit, Energy Centre, Computer Room and upgrades to critical site wide infrastructure. This means it will be capable of providing emergency care after a major disaster.
Dec 2019 The NZ Government issued a Notice of Information for the upcoming tender opportunity for pre-construction and construction service delivery of the hospital upgrade.
Feb 2020 The RFP for the pre-construction services contract was released.
Jul 2020 The Taranaki District Health Board appointed Leighs Construction as the preferred bidder for the project. This includes Early Contractor Involvement services and the Seismic Risk Management Plan.
May 2021 Construction commencement New East Wing Building.
Jun 2022 Taranaki DHB and Leighs Construction signed the Main Works Contract for construction of the New East Wing Building for the project.
Nov 2022 Designs were released for the Cancer Centre.
Mar 2023 The new Renal Unit officially opened to patients.
Oct 2023 Construction commenced on the Cancer Centre following completion of demolition of the old laundry building. Leighs Construction is also delivering the Cancer Centre works.
May 2025 The New Zealand Government announced an additional $59.2 million for the project to ensure Stage Two is complete by the end of 2025. The funding will support the delivery of the new East Wing Building.
Jun 2026 The New Zealand Government announced the formal commencement of operations at the new East Wing Building, marking the completion of Stage Two of the project.