The Teebar BESS is a 400-megawatt / 1.6-gigawatt hour Battery Energy Storage System proposed by Atmos Renewables. The project is expected to connect to the National Electricity Market via the adjacent Powerlink Teebar Creek Substation, 80 kilometres north-west of Gympie, Queensland.
Key Dates
| Dec 2025 | Contract Award |
| 2026 | Expected Construction Commencement |
| Mar 2028 | Expected Construction Completion |
Procurement
| Procuring Agency: | Atmos Renewables |
| Successful Tenderer: | Enerven |
| Procurement note: | The contract is being delivered through an Early Contractor Involvement (ECI) Balance of Plant agreement. |
| Related contracts: |
PROJECT HISTORY
| Nov 2024 | The project was granted development approval from the Fraser Coast Regional Council. |
| Aug 2025 | A project summary was submitted to the Federal Department of Industry, Science and Resources, seeking an Australian Industry Participation Plan. |
| Sep 2025 | The project was awarded a Capacity Investment Scheme Agreement as part of the Capacity Investment Scheme Tender Round Three. |
| Dec 2025 | Atmos Renewables has signed an Early Contractor Involvement Agreement with Enerven. |
Sector
Energy
Procurement approach
Engineering, Procurement and Construction (EPC) |
Location
Queensland |
Resources