The Plains Wind Farm

PROJECT STATUS
Detailed Planning
The Plains Wind Farm

The Plains Wind Farm would comprise the construction of a 1,230-megawatt wind turbine wind farm located within the Plains Renewable Energy Park in the NSW South-West Renewable Energy Zone. 

The proposed infrastructure components would include: 

  • 171 wind turbine generators
  • electrical reticulation works 
  • access roads, and
  • ancillary infrastructure.

Key Dates

Nov 2022 Project Announcement
2027 Expected Construction Commencement
2031 Expected Construction Completion

Procurement

Procuring Agency: ENGIE

PROJECT HISTORY

Nov 2022 The NSW Department of Planning and Environment published ENGIE's Request for the Secretary's Environmental Assessment Requirements (SEARs) and Scoping Report for the project.
Dec 2022 The NSW Department of Planning and Environment Secretary's Environmental Assessment Requirements were issued for the preparation of the Environmental Impact Statement of the project.
May 2024 The project's Environmental Impact Statement (EIS) was published and the project placed on exhibition, closing 4 June. The EIS indicated a revised proposal of a 1,350 MW wind farm, reduced from 1,800 MW.
Aug 2025 ERM submitted an updated Amendment Report to the NSW Major Projects Portal. The report proposes a reduction in the number of turbines to 171 with a 1.2 GW capacity.