Major Contract

Stage One - Brownfield Package

PROJECT STATUS
Awarded
Stage One - Brownfield Package

The Wave - Stage One will see delivery of a 19-kilometre dual-track heavy rail network between Beerwah and Caloundra and is being delivered across three packages:

  • Greenfield package 
  • a Brownfield package, and 
  • ECTS and Digital Radio Systems 

The scope of the Brownfield Package comprises: 

  • upgrade of Beerwah Station
  • new grade separated rail junction north of Beerwah Station, including grade separation for Steve Irwin Way
  • connection to the existing North Coast Line, and
  • integration with the Beerburrum to Nambour Rail Upgrade (Stage 1) project.

Key Dates

Nov 2024 ROIs Open
Dec 2024 ROIs Close
Jan 2025 EOIs Open
May 2026 Preferred Bidder Selection

Procurement

Successful Tenderer: Beerwah Coast Connect - a consortium of Georgiou, Hatch and Laing O’Rourke
Procurement note:

The project is being delivered using a pre-construction design and construct model, with the consortium selected for the pre-construction contract to be awarded a main works Alliance contract subject to pre-construction performance. The model is closely aligned to the model being used on the Logan and Gold Coast Faster Rail–Rail Package.

PROJECT HISTORY

Nov 2024 The Queensland Government commenced a joint Registration of Interest (ROI) process for the delivery of Greenfield and Brownfield packages, closing 10 December.
Jun 2025 The 2025-26 QLD Budget repackaged the project from Direct Sunshine Coast Rail Line Stage One to Rail Infrastructure Improvements – North Coast. $140 million was allocated to the project in FY2025-26.
May 2026 A design and pre-construction contract was awarded to the Beerwah Coast Connect, a consortium of Georgiou, Hatch and Laing O’Rourke.
Sector
Rail
Procurement approach
Alliance |
Location
Queensland |
Resources