Project

Tomago Battery Energy Storage System

PROJECT STATUS
Under Delivery
Tomago Battery Energy Storage System

The Tomago Battery Energy Storage System (BESS) is an energy storage being developed on the Tomago Industrial Estate, in the Hunter-Central Coast Renewable Energy Zone. The scope of the works includes:

  • a 500 megawatt / 2,000 megawatt hour BESS
  • transmission connection to either the Transgrid Tomago 132 kilovolt or the Transgird Tomago 330 kilovolt substation through two potential transmission routes
  • site infrastructure, including use of the approved Newcastle Power Station off-site laydown area, an office and maintenance buildings, control rooms, warehouses, site access, internal roads, parking, lighting and fencing.

Key Dates

Aug 2025 Contract Award
Dec 2025 Construction Commencement
2027 Expected Construction Completion

Procurement

Procuring Agency: AGL
Successful Tenderer: Fluence

PROJECT HISTORY

Mar 2023 The Request for the Secretary's Environmental Assessment Requirements (SEARs) was submitted for the project.
May 2023 SEARs was issued for the project.
Nov 2023 The project's Environmental Impact Statement was placed on public exhibition, closing 13 December.
Nov 2024 The project received development approval from the NSW Government. The approved Assessment Report provided a total estimated cost of $1.1 billion, with construction expected to commence in 2026 and be completed in 2029.
Jul 2025 AGL has awarded the Engineering, Procurement and Construction (EPC) contract to Fluence, following a Final Investment Decision announcement.
Dec 2025 AGL announced that construction has commenced, with operations targeted for the the second half of 2027.
Estimated Total Cost
(2025)
Sector
Energy
Procurement approach
Engineering, Procurement and Construction (EPC) |
Location
New South Wales |
Resources
Project pages
AGL Project Page