The Tonkin Highway is a 44-kilometre north-south highway and partial freeway in Perth, Western Australia, linking Perth Airport with the city's north-eastern and south-eastern suburbs.
The WA Government has been progressively undertaking improvements to the Highway's corridor across four projects.
- Tonkin Highway Gap
- Tonkin Highway Extension Stage Three
- Tonkin Highway Grade Separations, and
- North Ellenbrook Interchange.
The Grade Separations project will see Tonkin Highway widened from four to six lanes and grade separations delivered at Hale Road, Welshpool Road and Kelvin Road.This project is to be delivered using two Design and Construct contracts.
- Hale Road and Welshpool Road, and
- Kelvin Road.
The Kelvin Road contract will see an interchange delivered at Kelvin Road and the balance of Tonkin Highway widening.
Key Dates
Oct 2024 | EOIs Open |
Nov 2024 | EOIs Close |
Jan 2025 | RFP Open |
Apr 2025 | RFP Close |
Jun 2025 | Expected Contract Award |
Aug 2025 | Expected Contract Award |
Aug 2025 | Expected Construction Commencement |
Dec 2025 | Expected Construction Completion |
Funding contributions
Federal Government | |
WA Government | |
The Federal and WA Government have provided joint funding for both grade separation contracts. The total funding for each contract has not been publicised. These funding contributions represent the total value of both contracts. |
Procurement
Procuring Agency: | Main Roads Western Australia |
PROJECT HISTORY
May 2019 | The project was allocated funding as part of a $1.2 billion funding package announced in the 2019-20 WA Budget. |
Aug 2021 | The Government of Western Australia released new designs for Tonkin Highway and Hale Road interchange following community consultation. The new designs directly connect Tonkin Highway northbound and Hale Road via a new road that will be constructed alongside the highway. |
Sep 2021 | Following a review of its Asset Investment Program, the WA Government announced a delay to the project's completion. The Welshpool Road and Hale Road projects have been deferred by one year, and completion is expected in mid-2025. |
May 2022 | The 2022-23 WA Budget allocated an additional $250 million toward the Tonkin Highway Grade Separations at Hale, Welshpool and Kelvin Roads and Stage Three Extension projects. |
Oct 2024 | The Government of Western Australia commenced procurement for the project, issuing an Expression of Interest for a Design and Construct contract for the interchanges at Hale Road and Welshpool Road. |