The proposed Wambo Wind Farm, located near Jundowae within the Queensland Southern Renewable Energy Zone (REZ), will be delivered in two stages. Stage One will include a 252-megawatt wind farm comprising 42 turbines. The scope of Stage Two will comprise an additional 41 turbines with 254-megawatts of additional generating capacity.
The project is a joint venture between Cubico Sustainable Investments and publicly-owned Stanwell Corporation.
Key Dates
2018 | Project Announcement |
2023 | Construction Commencement |
2026 | Expected Construction Completion |
Funding contributions
Queensland Government |
PROJECT HISTORY
2018 | Renewable Energy Partners (REP) announced the project. |
2019 | Renewable Energy Partners and Cubico Sustainable Investments agreed to co-develop the project. Following construction, Cubico Sustainable Investments is expected to be the long-term owner and operator of the Wambo Wind Farm. |
Oct 2020 | The Queensland Government granted the Wambo Wind Farm planning approval. |
Mar 2022 | The Queensland Government announced a $193 million allocation for the project. |
Jun 2023 | Construction commenced on the project. |
Feb 2024 | The Queensland Government approved the second stage of the project. |
Sector
Energy
Procurement approach
Market Led Proposal |
Location
Queensland |