Project

Wambo Wind Farm

PROJECT STATUS
Under Delivery
Wambo Wind Farm

The Wambo Wind Farm, located near Jundowae within the Queensland Southern Renewable Energy Zone, is a 506MW wind farm, to be delivered over two stages.

  • Stage One will include a 252-megawatt wind farm comprising 42 turbines.
  • Stage Two will include an additional 41 turbines with 254 megawatts of additional generating capacity.

The project is a joint venture between Cubico Sustainable Investments and publicly-owned Stanwell Corporation.

Key Dates

2018 Project Announcement
2023 Construction Commencement
2026 Expected Construction Completion

Funding contributions

Queensland Government

Procurement

Procuring Agency: Cubico Sustainable Investments
Successful Tenderer: EPC contractor: Vestas Civil BoP: Fulton Hogan (stage one), Bielby (stage two) Electrical BoP: Yurika (stages one and two)
Related contracts:
Turbine Supply
Successful Tenderer - Vestas

PROJECT HISTORY

2018 Renewable Energy Partners (REP) announced the project.
2019 Renewable Energy Partners and Cubico Sustainable Investments agreed to co-develop the project. Following construction, Cubico Sustainable Investments is expected to be the long-term owner and operator of the Wambo Wind Farm.
Oct 2020 The Queensland Government granted the Wambo Wind Farm planning approval.
Mar 2022 The Queensland Government announced a $193 million allocation for the project.
Jun 2023 Construction commenced on the project.
Feb 2024 The Queensland Government approved the second stage of the project.
Jun 2025 Commissioning and testing of first turbines commenced prior to Stage 1 operations commencing in late 2025.
Sector
Energy
Procurement approach
Market Led Proposal | Other |
Location
Queensland |
Resources
Project website
Wambo Wind Farm