Watta Wella Renewable Energy Project

PROJECT STATUS
Announced
Watta Wella Renewable Energy Project

The Watta Wella Renewable Energy Project is a proposed hybrid Wind, Solar and Battery facility located near Stawell, VIC. The scope of the project includes delivery of:

  • a 47 turbine Wind Farm with a maximum generation capacity of 376 MW,
  • a 85 MW Solar Farm,
  • a 400 MW / 1.6 GWh Battery Energy Storage System, and 
  • ancilliary infrastructure, including underground cabling, on-site substation, and operations and maintenence facility.

The project will connect to the NEM via the adjacent Bulgana substation.

Procurement

Procuring Agency: RES

PROJECT HISTORY

Jul 2022 A planning referral was submitted to the Victorian Department of Transport and Planning for assessment.
Sep 2022 The project was referred to the EPBC Portal for Federal environmental assessment.
Nov 2022 The Federal Department of Climate Change, Energy, the Environment and Water determined the project was a controlled action under the EPBC Act. The project will be assessed under a bilateral assessment agreement with Victoria.
Jun 2026 The Victorian Department of Transport and Planning granted planning approval to the project.
Estimated Total Cost
(2022)
Sector
Energy
Procurement approach
Unconfirmed |