WestConnex Stage One involves improvements and extensions of the existing M4 in two parts:
- Stage 1A - M4 Widening: widening the M4 from six to eight lanes between Parramatta and Homebush, and
- Stage 1B - New M4 Tunnels: extending the M4 (M4 East) from Homebush to Haberfield via Concord with 5.5 kilometres of new three-lane tunnel, inclduing provision for the connection to the M4-M5 Link (WestConnex Stage Three).
Key Dates
| Dec 2014 | Contract Award | 
| Mar 2015 | Construction Commencement | 
| Jul 2017 | Construction Completion | 
Funding contributions
| User charges | 
Procurement
| Successful Tenderer: | CPB Contractors, and Rizzani de Eccher Joint Venture. | 
PROJECT HISTORY
| Dec 2014 | The contract was awarded to a CPB Contractors and Rizzani de Eccher Australia Joint Venture. | 
| Mar 2015 | Construction commenced on the project. | 
| Jul 2017 | Construction on the WestConnex Stage 1A - M4 Widening was completed. | 
| Aug 2017 | Following a one month toll-free period, a distanced-based toll between $1.77 - $4.56 was implemented on the widened M4. | 
                     Estimated Total Cost
                  
                  
                                          
                        (2015)
                     
                  
               Sector
               Road
            Procurement approach
               
                                                               Traditional Procurement  | 
                                                      
            Location
               
                                                               New South Wales |
                                                      
               Resources
                
            