WestConnex Stage 1B - New M4 Tunnels

PROJECT STATUS
Operational
WestConnex Stage 1B - New M4 Tunnels

WestConnex Stage One involves improvements and extensions of the existing M4 in two parts:

  • Stage 1A - M4 Widening: widening the M4 from six to eight lanes between Parramatta and Homebush, and 
  • Stage 1B - New M4 Tunnels: extending the M4 (M4 East) from Homebush to Haberfield via Concord with 5.5 kilometres of new three-lane tunnel, inclduing provision for the connection to the M4-M5 Link (WestConnex Stage Three).

Key Dates

Jun 2015 Contract Award
Jul 2016 Construction Commencement
Jul 2019 Construction Completion

Funding contributions

User charges

Procurement

Successful Tenderer: New M4 Tunnels: CPB Contractors, Samsung and John Holland Joint Venture

PROJECT HISTORY

Mar 2015 Early works commenced.
Jun 2015 The design and construct contract to deliver the New M4 Tunnels was awarded to a Leighton Contractors, Samsung C&T and John Holland consortium.
Jun 2016 Major construction works commenced.
Jul 2019 The project reached construction completion and commenced operations.
Estimated Total Cost
(2015)
Sector
Road
Procurement approach
Traditional Procurement |
Location
New South Wales |