Major Contract

Westport - Kwinana Bulk Terminal Redevelopment - Marine Infrastructure

PROJECT STATUS
Under Procurement
Westport - Kwinana Bulk Terminal Redevelopment - Marine Infrastructure

The Kwinana Bulk Terminal Redevelopment - Marine Infrastructure project will see the delivery of marine-side infrastructure works required as part of the broader Westport - Kwinana Bulk Terminal redevelopment. The Marine Infrastructure project comprises works across five packages:

  • Package One - design and procurement of longer lead time items
  • Package Two - marine construction, including delivery of a two-berth wharf and associated infrastructure
  • Package Three - civil construction, including seawall revetments, a 1.4 kilometre access causeway and drainage
  • Package Four - dredging of berth pockets and turning basin, and
  • Package Five - handover and commissioning

Westport has indicated that Package Four (Dredging) is an optional works package that may be procured separately.

Key Dates

Jul 2026 EOIs Open
Jun 2027 Expected Contract Award
Apr 2028 Expected Construction Commencement
Aug 2029 Expected Construction Completion

Procurement

Procuring Agency: Westport

PROJECT HISTORY

Jul 2026 Westport called for Expressions of Interest (EOIs) for the Kwinana Bulk Terminal Redevelopment - Marine Infrastructure Project. The scope of works, to be delivered under a Design and Construct contract, comprises a two-berth wharf, an approach jetty and transfer platform, seawall revetments and a reclaimed access causeway, with the dredging component of the marine works offered as an optional package within this EOI process. EOIs close 13 August.
Sector
Other Transport
Procurement approach
Design and Construct (D&C) |