Project

Whaleback Ridge Renewable Energy Project

PROJECT STATUS
Detailed Planning
Whaleback Ridge Renewable Energy Project

The Whaleback Ridge Renewable Energy Project, located around Lake Pieman near Zeehan in western Tasmania, will involve the establishment of up to 500 wind turbine generators, with a projected generating capacity of 3,000 megawatts (MW).

The proponent, Westcoast Renewable Energy, has identified a wide area of turbine exclusion zones. The Project includes the development of collector substations, access roads, office and workshop facilities, installation of overhead and underground transmission lines, and the use of mobile concrete batching plants.

The project will be staged to meet demand in the market and capacity on the transmission network, with an expectation that all project stages are likely to be constructed and operational by 2040, depending on market demand.

Key Dates

Mar 2024 Declared a major project
Jul 2026 Expected Construction Commencement
Jan 2040 Expected Construction Completion

Procurement

Procuring Agency: Westcoast Renewable Energy

PROJECT HISTORY

2019 Initial community consultation on the project commenced.
Oct 2023 The Major Project Proposal was lodged to the Tasmanian Planning Commission.
Mar 2024 The Tasmanian Minister for Planning declared the proposal a major project, enabling detailed planning.
Major Contract

Whaleback Ridge Renewable Energy Project Stage One

PROJECT STATUS
Detailed Planning
Whaleback Ridge Renewable Energy Project Stage One

The Whaleback Ridge Renewable Energy Project, located around Lake Pieman near Zeehan in western Tasmania, will involve the establishment of up to 500 wind turbine generators, with a projected generating capacity of 3,000 megawatts (MW).

The first stage of the development would see the delivery of approximately 45 turbines with a renewable energy capacity of 288 MW.

Key Dates

Mar 2024 Declared a major project
2025 Procurement expected to commence
2026 Expected Construction Commencement
2028 Expected Construction Completion

Procurement

Procuring Agency: Westcoast Renewable Energy

PROJECT HISTORY

Jan 2019 Initial community consultation on the project commenced.
Oct 2023 The Major Project Proposal was lodged to the Tasmanian Planning Commission.
Mar 2024 The Tasmanian Minister for Planning declared the proposal a major project, enabling detailed planning.