Whyalla Hydrogen Facility - Hydrogen Jobs Plan

PROJECT STATUS
Prospective
Whyalla Hydrogen Facility - Hydrogen Jobs Plan

The Whyalla Hydrogen Facility, also referred to as the Hydrogen Jobs Plan, is a proposed electrolyser, storage, and  generation project to be located in Whyalla, SA. 

The scope of the works includes delivery of: 

  • a 250-megawatt (MW) hydrogen production facility
  • a 200 MW hydrogen power plant, and 
  • 3,600 tonnes of hydrogen storage. 

The project will be delivered using separate hydrogen delivery and hydrogen storage packages.

Hydrogen Power South Australia, a new government enterprise, has been established to own and operate the hydrogen power plant.

Key Dates

Jun 2022 Project Announcement
Dec 2022 RFP Open
Mar 2023 RFP Close
Oct 2023 Preferred Bidder Selection

Funding contributions

SA Government

In February 2025, the Federal and SA Government announced funding for the project would be redirected to the Whyalla Steelworks operations, with funding for the hydrogen plant deferred.

Procurement

Procuring Agency: Hydrogen Power South Australia
Successful Tenderer: Hydrogen delivery package: ATCO Australia and BOC Consortium. Hydrogen storage facility: EPIC Energy.
Related contracts:
Hydrogen turbine supplier
Successful Tenderer - GE Vernova

PROJECT HISTORY

Jun 2022 The South Australian Government announced the project in it 2022/23 Budget.
Dec 2022 A Request for Proposal phase was opened to deliver the project, closing 14 March, 2023.
Oct 2023 The Government of South Australia announced the preferred bidders for the project and announced the project will be delivered using separate hydrogen delivery and hydrogen storage packages. A consortium comprising ATCO Australia and BOC, a Linde subsidiary, was selected as the preferred hydrogen delivery bidder to deliver an Early Contractor Involvement (ECI) phase. A separate ECI agreement has been made with EPIC Energy for the delivery of pipeline and hydrogen storage facility.
Feb 2024 The Government of South Australia announced GE Vernova as the preferred supplier for the hydrogen turbines. Additionally, it was confirmed that 82 new cabins would be built to accommodate workers on the Hydrogen Jobs Plan.
Jun 2024 The 2024-25 SA Budget allocated $389 million to the project.
Nov 2024 The Government of South Australia formally entered into an agreement with ATCO Australia to contract GE Vernova to supply four hydrogen turbines for the project.
Feb 2025 The Federal and SA Governments announced the deferral of the project, due to funding being reallocated for Whyalla Steelworks, which entered administration.
Jun 2025 The 2025-26 South Australian Budget confirmed the project has been deferred, with the Budget allocating $12 million over the next four years to enable the divestment of hydrogen-enabled gas turbines, acquired as part of the Jobs Plan.
Estimated Total Cost
(2022)
Sector
Energy