Landside Civil and Building Works package involves the construction of:
- roads and their connections to external roads and car parks
- connections to external utilities, and
- landside infrastructure and facilities.
Landside infrastrucuture and facilities comprise of:
- a water and wastewater complex
- a waste disposal facility
- an airport ground maintenance facility
- mechanical workshop facilities
- flammable and hazardous materials storage
- utility buildings
- access control points
- emergency operations centre
- landscaping, and
- security fencing.
Key Dates
| 2021 | Expected Contract Award |
| Dec 2021 | Contract Award |
| Mar 2023 | Construction Commencement |
| Dec 2024 | Construction Completion |
| 2026 | Expected Airport Operations Commencement |
Procurement
| Procuring Agency: | Western Sydney Airport |
| Successful Tenderer: | Aerowest Joint Venture (a joint venture between BMD Constructions Pty Ltd and Seymour Whyte Constructions Pty Ltd) |
PROJECT HISTORY
| Mar 2020 | Western Sydney Airport invited Registration of Interest for the package, closing on 21 April. Expression of Interest process was expected to begin in September, with contract award expected in fourth quarter of 2021. |
| Dec 2021 | Western Sydney Airport awarded the project's construction contract to the Aerowest Joint Venture, a joint venture between BMD Constructions Pty Ltd and Seymour Whyte Constructions Pty Ltd, following a competitive procurement process. |
| Dec 2024 | BMD Constructions confirmed the construction of the project was completed, ahead of the Airport opening in 2026. |
Sector
Other Transport
Procurement approach
Traditional Procurement |
Location
New South Wales |