The Wyaralong Water Treatment Plant project would provide a new treatment plant downstream from the Wyaralong Dam, and a connection to the SEQ Water Grid to service the Beaudesert and southern Logan areas.
The project has an intended capacity to treat 120 megalitres per day and is expected to be located on the north bank of the Logan River, approximately 500 metres from the existing Ceder Grove Weir.
Key Dates
Feb 2025 | ROIs Open |
Mar 2025 | ROIs Close |
Mar 2025 | EOIs Open |
Aug 2025 | Early Contractor Involvement Tender Open |
Jun 2027 | Expected Construction Commencement |
2031 | Operations/Service Commencement |
Procurement
Procuring Agency: | Seqwater |
Procurement note: | The procurement process includes two separate contracts – a Design and Construction (D&C) contract and a separate Operations and Maintenance contract, being procured simultaneously. The D&C contract is expected to also comprise the successful operator to contribute to the project’s design. |
PROJECT HISTORY
Feb 2025 | Seqwater hosted an industry briefing for the project, and subsequently called for Registrations of Interest for the project. |
Sector
Water & Sewerage
Procurement approach
Traditional Procurement |
Location
Queensland |
Resources