Yanco Delta Wind Farm would comprise a 1.5-gigawatt wind generation project and an 800-megawatt (MW) / 800-megawatt-hour (MWh) battery, to be located in the South-West Renewable Energy Zone (REZ) in NSW.
The scope of the works includes:
- up to 208 wind turbines to a maximum tip height of 270 metres
- an 800-MW / 800-MWh battery energy storage facility
- grid connection infrastructure
- wind monitoring masts, and
- a central primary substation and up to eight collector substations.
Key Dates
| 2025 | Expected Contract Award |
| 2026 | Expected Construction Commencement |
| 2029 | Expected Construction Completion |
Financing
| Debt Finance: | Origin Energy |
|
Origin Energy has entered into an agreement with Virya Energy to acquire its Yanco Delta Wind Farm. The purchase price and development expenditure prior to commencement of construction will be funded from Origin’s corporate debt facilities. The consideration consists of an upfront payment of $125 million to Virya Energy and an additional variable payment of up to $175 million conditional on the project achieving certain development milestones. |
|
Procurement
| Procuring Agency: | Origin Energy |
PROJECT HISTORY
| Apr 2022 | A scoping report for the project was published alongside a request for the Secretary's Environmental Assessment Requirements (SEARs). |
| May 2022 | SEARs were issued for the project. |
| Jun 2022 | Supplementary SEARs were issued for the project. |
| Nov 2022 | The NSW Department of Planning and Environment placed the project's Environmental Impact Statement on public exhibition, closing on 15 December. |
| Dec 2023 | The project received planning approval from the NSW Government. |
| Feb 2024 | The project received Commonwealth environmental approvals. |
| Apr 2024 | Origin Energy agreed with Virya Energy to acquire the Yanco Delta Wind Farm. The purchase price and development expenditure prior to commencement of construction will be funded from Origin’s corporate debt facilities. The consideration consists of an upfront payment of $125 million to Virya Energy and an additional variable payment of up to $175 million conditional on the project achieving certain development milestones. |
| Apr 2025 | EnergyCo allocated 1,460 megawatts of transmission access rights to Origin for the project as part of the South West Renewable Energy Zone. This enables the progression of development activities that will support a Final Investment Decision, targeted for early 2027. The project was the only project of four to receive access rights for its full scope. |
| Mar 2026 | The project was endorsed through the first round of the NSW Government's Investment Delivery Authority (IDA). IDA-endorsed projects will receive Government support in progressing through mandatory planning and approval pathways. |
Sector
Energy
Procurement approach
Other |